Aerial photo Methuen rotary before and after construction


What's Being Done?

MassDOT is reconstructing the I-93 Exit 46 interchange at Routes 110 and 113 in Methuen, replacing the existing rotary with a partial cloverleaf interchange. The project will alleviate traffic congestion and improve safety. Key elements of the project include:

  • building new I-93 southbound on-ramp and off-ramp to a realigned Route 110/113;
  • realigning two existing off-ramps;
  • constructing new signalized intersections east and west of the interchange;
  • constructing two noise barriers; and
  • adding bicycle lanes and sidewalks for improved access.

Traffic Advisory - April 21, 2015 through April 23, 2015

A daytime detour will be in place on Riverside Drive each day. Please go to the Traffic Advisories page for full details.

Upcoming Work - April 2015

Work on I-93 over the rotary and at the new and existing ramp locations continues.

View the Construction Update page for more information on construction activities and lane closures.

Construction includes:

  • Removal of contaminated soil at mitigation area at 18 Lowell Boulevard
  • Work on drainage operations at the existing and proposed ramps at I-93 Northbound and I-93 Southbound

Sign up for Methuen Rotary Reconstruction Project updates to keep current on traffic management plans and other important updates.

 


   

Construction Facts

Start Date: July 2014
End Date: Spring 2018
Cost: $66.4 million
Contractor: E.T. & L. Corp.

   


Rebar has been placed for construction of the center pier of the new bridge carrying I-93 over Route 110/113Structural steel beams are installed for the temporary widening of I-93 SB over Route 110/113. The temporary widening of the existing rotary bridges will allow MassDOT to maintain three travel lanes in each direction during construction. Once the new bridge is complete, the old and temporary bridges will be demolished.