Aerial photo Methuen rotary before and after construction

What's Being Done?

MassDOT is reconstructing the I-93 Exit 46 interchange at Routes 110 and 113 in Methuen, replacing the existing rotary with a partial cloverleaf interchange. The project will alleviate traffic congestion and improve safety. Key elements of the project include:

  • building new I-93 southbound on-ramp and off-ramp to a realigned Route 110/113;
  • realigning two existing off-ramps;
  • constructing new signalized intersections east and west of the interchange;
  • constructing two noise barriers; and
  • adding bicycle lanes and sidewalks for improved access.

Upcoming Work - October 2015

Work on I-93 over the rotary and at the new and existing ramp locations continues.

View the Construction Update page for more information on construction activities and lane closures.

Construction includes:

  • Install noise wall foundations and wall panels
  • Install retaining walls at Ramps B-C
  • Form and place bridge deck concrete at the center section of the I-93 bridge over relocated Route 110/113 
  • Form and place barrier concrete at the permanent widening at the north and southbound sides of the  I-93 over Riverside Drive bridge

The contractor has implemented the Stage 2B Temporary Traffic Control Plan. This traffic shift will be in place into spring 2016. View the Traffic Advisories page for details.

Sign up for Methuen Rotary Reconstruction Project updates to keep current on traffic management plans and other important updates.



Construction Facts

Start Date: July 2014
End Date: Spring 2018
Cost: $66.4 million
Contractor: E.T. & L. Corp.


Construction has begun for the  I-93 northbound on-ramp from Routes 110/113Steel rebar being placed for I-93 bridge deck over the relocated Route 110/113.