Aerial photo Methuen rotary before and after construction


What's Being Done?

MassDOT is reconstructing the I-93 Exit 46 interchange at Routes 110 and 113 in Methuen, replacing the existing rotary with a partial cloverleaf interchange. The project will alleviate traffic congestion and improve safety. Key elements of the project include:

  • building new I-93 southbound on-ramp and off-ramp to a realigned Route 110/113;
  • realigning two existing off-ramps;
  • constructing new signalized intersections east and west of the interchange;
  • constructing two noise barriers; and
  • adding bicycle lanes and sidewalks for improved access.

The Methuen Rotary project was highlighted in a segment of Methuen Community Television's September 2015 Methuen Now program.

Upcoming Work - May 2016

Work on I-93 over the rotary and at the new and existing ramp locations continues.

View the Construction Update page for more information on construction activities and lane closures.

Construction includes:

  • Begin landscape work near Smith Avenue and new I-93 ramps
  • Pave sections of Route 110/113 east and west of the rotary
  • Complete paving new I-93 southbound off-ramp and prepare for opening in June

The contractor has implemented the Stage 2B Temporary Traffic Control Plan. This traffic shift will be in place into spring 2016. View the Traffic Advisories page for details.

Sign up for Methuen Rotary Reconstruction Project updates to keep current on traffic management plans and other important updates.


   

Construction Facts

Start Date: July 2014
End Date: Spring 2018
Cost: $66.4 million
Contractor: E.T. & L. Corp.

   


New Deck at Permanent Widening of I-93 Northbound Bridge over Riverside Drive

Paving at I-93 southbound
off-ramp near Valley Office Park.
Ramp is expected to open to traffic in June.