Anticipated Construction Schedule

An estimated construction schedule and sequence is shown below. Weather may impact the schedule as shown.

Total construction duration less than 4 years

Completed construction:

  • Stage 1 - completed April 2015
  • Stage 2A - completed August 2015
  • Stage 2B - completed December 2015
  • Stage 2C - completed July 2016
  • Stage 3A - completed November 2016

Stage 3B - November 2016 to April 2017

  • Open new I-93 southbound on-ramp for westbound traffic on Rte. 110/113
  • Continue demolition of existing rotary bridges and placing fill
  • Begin work to reconstruct I-93 median and median barrier

Stage 3C - April 2017 to August 2017

  • Continue demolition of existing rotary bridges
  • Complete new I-93 northbound off-ramp

Stage 4 - August 2017 to Spring 2018

  • Remove temporary I-93 median paving
  • Install median concrete barrier
  • Complete final I-93 paving and striping
  • Construction complete Spring 2018