Construction Updates

During the month of September, the following activities will continue on the I-93 at Routes 110 and 113 Interchange Reconstruction – Methuen Rotary project:

  • Continue to work on lighting on Route 110/113
  • Work on traffic signals at Bolduc/Riverside/Route 110 intersection
  • Continue to excavate for permanent sedimentation and infiltration basins
  • Continue installing curbing and sidewalks
  • Pave sections of Route 110/113 east and west of I-93
  • Install drainage at I-93 Northbound along Northbound on ramp
  • Install drainage at I-93 Southbound along Southbound off ramp
  • Mill and pave I-93 Southbound
  • Mill and pave I-93 Northbound
  • Install permanent signs
  • Continue with earthwork and paving at I-93 Northbound off ramp to Route 110/113 East
  • Continue installing guardrail and fencing
  • Continue with landscaping

Work hours on the project are:

  • For daytime work on I-93 – 5:30 am to 5:30 pm
  • For nighttime work on I-93 – 8:00 pm to 5:00 am
  • For daytime work on local roads – 7:00 am to 3:30 pm

Lane Closures:

  • Single lane closures can be expected on I-93 Northbound from 5:30 am to 2:00 pm
  • Single lane closures can be expected on I-93 Southbound from 10:00 am to 2:00 pm
  • Double lane closures can be expected on I-93 Southbound from 10:00 pm to 5:00 am
  • Single lane closures can be expected on local roads from 9:00 am to 3:00 pm