Construction Updates

During the month of June, the following activities will continue at the I-93/Routes 110 and 113 Interchange where MassDOT has removed the rotary:

  • Continue removing remaining sections of rotary bridges
  • Continue placing fill for embankment for new I-93 northbound off ramp to Route 110/113 west and continue work on I-93 northbound off ramp to Route 110/113 east
  • Continue work on lighting on Route 110/113
  • Work on traffic signals at Bolduc/Riverside/Route 110 intersection
  • Continue to excavate for permanent sedimentation and infiltration basins
  • Continue roadway excavation and paving at Route 110/113 east and west of I-93
  • Pave sections of Route 110/113 east & west of I-93
  • Continue installing guardrail, fencing and landscaping

WORK HOURS:

  • For daytime work on I-93 - 5:30 am to 5:30 pm
  • For nighttime work on I-93 - 8:00 pm to 5:00 am
  • For daytime work on local roads - 7:00 am to 3:30 pm

EXPECTED LANE CLOSURES:

  • Single lane closures can be expected on I-93 northbound from 5:30 am to 2:00 pm
  • Single lane closures can be expected on I-93 southbound from 10:00 am to 2:00 pm
  • Double lane closures can be expected on I-93 southbound from 10:00 pm to 5:00 am
  • Single lane closures can be expected on local roads from 9:00 am to 3:00 pm